Sequifi 2026 Delivery Roadmap

Annual overview of quarterly deliverables across all teams

Q1 Jan - Mar
35 / 42
Tasks Completed
Q2 Apr - Jun
0 / 17
Tasks Completed
Q3 Jul - Sep
-
Not yet planned
Q4 Oct - Dec
-
Not yet planned
Q1 - January to March Jan 1 – Mar 31, 2026
View Detailed Plan Q1 Performance Report
Overall Completion76%
Q2 - April to June Apr 1 – Jun 30, 2026
View Detailed Plan
Overall Completion0%
TaskTeamStartEndStatusCompletion
Grow Marketing - Custom Config HighBuilds - BLOREApr 1Apr 8Completed
100%
Cost Optimization for Sequipay (Primarily Jobber) HighBuilds - BLOREApr 1Apr 30In Progress
90%
SequiDocs 3.0 CarryoverBuilds - BLOREApr 1May 6In Progress
80%
Jobber Partnership Integration with SequiPay CarryoverBuilds - BLOREApr 1Apr 18May 11 *In Progress
95%
Override Pool Evaluation CarryoverBuilds - BLOREApr 1Apr 18Completed · LIVE
100%
Marketplace API Development CarryoverBuilds - BLOREApr 1Apr 15Completed
100%
Infrastructure Cost Savings Analysis - SMB CarryoverBuilds - BLORE--On Hold
0%
Re-order drug test through Turn.aiBuilds - GGN--Blocked
0%
Importing company tax info mid quarter Critical PRD PendingBuilds - GGNApr 22May 6 »May 18Planned
0%
Reporting UX Overhaul High Handover PendingBuilds - GGNApr 27May 6 »May 18Planned
0%
Do Not Pay Handover ScheduledBuilds - GGNApr 29May 8 »May 19Planned
0%
Termination : Sequifi <> Worklio PRD PendingBuilds - GGN--Planned
0%
Remove IS Manager dependencyBuilds - GGN--Planned
0%
Plaid Verification - User OnboardingBuilds - GGN--Planned
0%
Worklio transfers position (1099 to W2) High Hold · Decision PendingBuilds - GGNApr 27May 7 »May 15In Progress
10%
Overnight SupportBuilds - GGNApr 20May 15Continuous
30%
Worklio New Pay Date API & Sync HighBuilds - GGN--Blocked
0%
Worklio Onboarding Flow change and Edge CasesBuilds - GGNApr 7Apr 27May 8 *In Progress
80%
Stack Split FeatureBuilds - GGNApr 9Apr 17Completed
100%
Worklio Payroll Processing UpdatesBuilds - GGNApr 1Apr 27May 8 *In Progress
80%
Recalculate on missing functions HighBuilds - NOIDAApr 7Apr 27May 5 *In Progress
95%
Pending Pay Verification HighBuilds - NOIDAApr 7Apr 24Completed
100%
Time/Hours Imports HighBuilds - BLOREApr 8Apr 27May 5 *In Progress
90%
Worklio Benefits (Full Integration)Builds - BLOREApr 1Apr 27 »May 31May 20 «In Progress
25%
Prismatic IntegrationsBuilds - BLOREApr 28ContinuousContinuous
0%
Template Based Server DeploymentPerf & Tech Debt--Planned
0%
Self Serve, Worklio KYC, Auto-DeployPerf & Tech DebtApr 3Apr 24May 5 *In Progress
90%
Sequifi - Mobile AppProductApr 1Jun 30Completed
100%
Ad-hoc Improvements and Enhancements High 7 / 8 Details hereBuilds - GGNApr 1Jun 30In Progress
88%
Ad-hoc Improvements and Enhancements High 4 / 8 Details hereBuilds - NOIDAApr 1Jun 30In Progress
50%
Ad-hoc Improvements and Enhancements High 0 / 3 Details hereBuilds - BLOREApr 1Jun 30In Progress
0%
Integrations Details hereIntegrations - GGNApr 1Jun 30Continuous
73%
Franchise Model LowBuilds - GGNApr 1May 31On Hold
0%
Worklio Time Clock/Attendance LowBuilds - BLORE--Not Planned
0%
Bugs (Support Team)Support--Continuous
...
Improvement (Support Team)Support--Continuous
...
Feature (Support Team)Support--Continuous
...
Request (Support Team)Support--Continuous
...
Misconfiguration (Support Team)Support--Continuous
...
Knowledge Gap (Support Team)Support--Continuous
...
Q3 - July to September Jul 1 – Sep 30, 2026
Not Yet Planned
Overall Completion-
TaskTeamStartEndStatusCompletion
Tasks will be planned closer to Q3. Check back later.
Q4 - October to December Oct 1 – Dec 31, 2026
Not Yet Planned
Overall Completion-
TaskTeamStartEndStatusCompletion
Tasks will be planned closer to Q4. Check back later.