Sequifi Q1 (JFM) 2026 Delivery Plan

Updated on: Mar 18, 2026

Team Rosters

Task Gantt

Schedule: January 20 – March 30, 2026

January
February
March
Jan 20 - Feb 2
Wk1Wk2
Feb 3 - 16
Wk1Wk2
Feb 17 - Mar 2
Wk1Wk2
Mar 3 - 16
Wk1Wk2
Mar 17 - 30
Wk1Wk2
Builds - GGN 10 dev
New Design System - Improvements New
Rishi (FE), Rushita (FE), Shreya Singh (FE), Lokendra (BE)
Deductions and Accruals
Jay (BE), Rishi (FE), Niti (BE)
Additional Offices Effective Dates New
Prem (BE)
Multi-Milestone Override Completed
Prem (BE), Ashutosh B (FE), External 1 (Full Stack), External 2 (Full Stack)
Office Override Completed
Sonam (BE)
New Design System Implementation Completed
Rishi (FE), Rushita (FE), Shreya Singh (FE), Lokendra (BE)
Worklio - PLAID Completed
Niti (BE), Ashutosh B (FE)
Chipr Stack Milestone Split Completed
Prem (BE)
Export Updates Completed
Lavejeet (BE)
Worklio - Onboarding Improvements Completed
Niti (BE)
Custom Sales Fields Completed
Prem (BE)
Worklio - Payroll Completed
Jay (BE)
Worklio - Reporting Completed
Jay (BE)
Support Worklio Implementation Completed
Jay (BE), Ashutosh B (FE)
Manager Override Completed
Prem (BE), Ashutosh B (FE), External 1 (Full Stack), External 2 (Full Stack)
Franchise Model Deferred
-
Worklio - Benefits Deferred
-
Worklio - eVerify Deferred
-
Sequifi Mobile App Deferred
-
Performance & Tech Debt - GGN 2 dev
Railway Implementation
Gorakh (BE)
Position and Employment Update Audit History
Gorakh (BE)
New Relic Performance Monitoring Completed
Gorakh (BE)
Audit Logs (Spatie) Completed
Yev (BE)
Composer 8.1 to 8.3 Completed
Yev (BE)
Backdating Positions Completed
Gorakh (BE)
New Server Creation - Automation Completed
Gorakh (BE)
Multi Tenancy Deferred
-
Designs - GGN 3 designers
UX Mapping and Improvements
Sarthak (Design), Tisha (Design)
Integrations - GGN 2 dev
Integrations Requests (New & Support Existing) Continuous
Farhan (Integrations), Rachna (Integrations)
Prismatic POC Completed
Farhan (Integrations)
Builds - NOIDA 7 dev
LMS Integration into Sequifi New
Neelesh (BE), Rushita (FE)
5 Decimal Update New
Neelesh (BE), Rushita (FE)
Pending Pay Verification Delayed Awaiting Handover
Pushkar Kalra (BE), Lekhni Bhatnagar (BE), Rushita (FE)
Training Completed
Entire NOIDA Team
Roofing Tiers Schema Updates Completed
Neelesh Krishna (BE), Aakash Upadhyay (BE), Rushita (FE)
Support 6 dev
Everee Config and Feature Flag New
Ashutosh Y (BE), Kunal (FE)
Support and Requests Continuous
Entire Support Team
Training Completed
Entire Support Team
Builds - BLORE 7 dev
Jobber Partnership Integration with SequiPay New
Abhilash (Lead)
SequiDocs 3.0
Abhilash (Lead)
Override Pool Evaluation New
Abhilash (Lead)
Marketplace API Development New
Abhilash (Lead)
Training
Likhith K (BE), Arun Kumar R (BE), Adarsh Maddheshiya (BE)
Infrastructure Cost Savings Analysis New Delayed
Abhilash (Lead)
Training Completed
Balasubramanian G (BE), Hemanth Nirmalkar (FE), Purvesh Ramoliya (BE), Mani Kandan (BE)
PODs Structure - Process and Implementation Deferred
-
New Design System - Improvements 90%
Deductions and Accruals 50%
Additional Offices Effective Dates 5%
Multi-Milestone Override
Office Override
New Design System Implementation
Worklio - PLAID
Chipr Stack Milestone Split
Export Updates
Worklio - Onboarding Improvements
Custom Sales Fields
Worklio - Payroll
Worklio - Reporting
Support Worklio Implementation
Manager Override
Franchise Model (Deferred)
Worklio - Benefits (Deferred)
Worklio - eVerify (Deferred)
Sequifi Mobile App (Deferred)
Railway Implementation 70%
Position and Employment Update Audit History 50%
New Relic Performance Monitoring
Audit Logs (Spatie)
Composer 8.1 to 8.3
Backdating Positions
New Server Creation - Automation
Multi Tenancy (Deferred)
UX Mapping and Improvements 10%
Integrations Requests (New & Support Existing)
Prismatic POC
LMS Integration into Sequifi New 80%
5 Decimal Update New 80%
Pending Pay Verification
Training
Roofing Tiers Schema Updates
Everee Config and Feature Flag 80%
Support and Requests
Training
Jobber Partnership Integration with SequiPay
SequiDocs 3.0
Override Pool Evaluation
Marketplace API Development
Training
Infrastructure Cost Savings Analysis
Training
PODs Structure - Process and Implementation (Deferred)

Task Schedule

Team Member Availability

Backlog Asks