Updated on: September 11, 2026
Schedule: July 1 – September 30, 2026 · Complete
Allocation and availability periods for each team member
| Team Member | Allocated | Tasks | Available |
|---|---|---|---|
| BUILDS - GURGAON | |||
| Jay (BE) | Through Jul 26 | Worklio | From Jul 27 |
| Niti (BE) | Through Jul 19 | Worklio | From Jul 20 |
| Prem (BE) | Through Jul 12 | Milestone Schema Update | From Jul 13 |
| Sonam (BE) | Through Jul 12 | Sales Closure Update | From Jul 13 |
| Rishi (FE) | Through Jul 12 | Onboarding Flow Audit (Rep) | From Jul 13 |
| BUILDS - NOIDA | |||
| Aakash (BE) | Through Jul 12 | Onboarding Flow Audit (Rep) | From Jul 13 |
| Nilesh (BE) | Continuous | Overnight Support | Partial |
| Ashutosh (BE) | Through Jul 12 | Server Templates | From Jul 13 |
| Rushita (FE) | Through Jul 12 | Support & Misc | From Jul 13 |
| BUILDS - BANGALORE | |||
| Deepak (BE) | Through Jul 19 | Retroactive Tiers | From Jul 20 |
| Purvesh (BE) | Through Jul 19 | Wages as Draws | From Jul 20 |
| Mani (BE) | Through Jul 12 | Audit API (Backend / Frontend) | From Jul 13 |
| Arun (BE) | Through Jul 12 | Gaya Integration | From Jul 13 |
| Bala (BE) | Continuous | Overnight Support | Partial |
| Likhith (BE) | Through Jul 12 | Tiers Audit | From Jul 13 |
| Hemant (FE) | Through Jul 12 | Wages as Draws | From Jul 13 |
| INTEGRATIONS - GGN | |||
| Farhan (BE) | Through Jul 12 | Arrive | From Jul 13 |
| Rachna (BE) | Through Jul 12 | Acculynx | From Jul 13 |
| SUPPORT | |||
| Naman (BE) | Continuous | Support Tickets | Partial |
| Anurag (BE) | Continuous | Support Tickets | Partial |
| Kunal (FE) | Continuous | Support Tickets | Partial |