All recurring meetings, frequency, duration, and participants
| Activity | Frequency | Duration | Participants |
|---|---|---|---|
| Stakeholder Refinement | Bi-weekly | 1-2 hrs | PO, FL, TL, Stakeholders |
| Design Review | Weekly | 1 hr | PO, FL, TL, UX/UI |
| PRD Creation | Per feature | 2-4 hrs | PO, FL, TL, Stakeholders |
| PRD Review/Sign-off | Per feature | 1 hr | PO, FL, TL, Stakeholders, QA Lead |
| Sprint Planning | Every 2 weeks | 2-4 hrs | FL, TL, SM, PC, Full Team |
| Daily Standup | Daily | 15 min | SM, PC, Dev Team, QA |
| Scrum of Scrums | Weekly | 30 min | FL, TL, all Scrum Masters |
| Technical Sync | Weekly | 1 hr | TL, Senior Devs from each team |
| Backlog Refinement | Mid-sprint | 1-2 hrs | PO, SM, PC, Full Team |
| Sprint Review | Every 2 weeks | 1-2 hrs | FL, TL, PC, Team + Stakeholders |
| Retrospective | Every 2 weeks | 1 hr | SM, PC, Team |
| Release Coordination | End of sprint | 1 hr | FL, TL, all SMs, QA Leads |
| Bug Triage | Daily | 30 min | Support Lead, TL (as needed) |
| RCA Meeting | Per P0 bug | 1 hr | TL, Developer, QA Lead, PM |
| Monthly Quality Review | Monthly | 1 hr | FL, TL, QA Lead, DevOps Lead |
Legend: FL = Functional Lead, TL = Technical Lead, SM = Scrum Master, PC = Project Coordinator, PO = Product Owner
When: Day 1 of Sprint
Duration: 2-4 hours
Attendees: PO, Functional Lead, Technical Lead, Scrum Master, PC, Dev Team, QA
When: Every day, same time
Duration: 15 minutes (strict)
Attendees: Scrum Master, PC, Dev Team, QA
Each member answers: What did I complete? What will I work on? Any blockers?
When: Mid-sprint (Day 4-5)
Duration: 1-2 hours
Purpose: Prepare items for NEXT sprint
When: Day 10 (last day of sprint)
Duration: 1-2 hours
Attendees: PO, Leads, Team, Stakeholders
When: Day 10 (after Review)
Duration: 1 hour
Attendees: Scrum Master, PC, Dev Team, QA
When: Weekly
Duration: 30 minutes
Attendees: Functional Lead, Technical Lead, all Scrum Masters
Purpose: Sync across teams, identify dependencies, resolve blockers
Format: Each SM shares: progress, blockers, dependencies on other teams
When: Weekly
Duration: 1 hour
Attendees: Technical Lead, Senior Devs from each team
Purpose: Architecture alignment, shared components, technical debt
When: End of Sprint
Duration: 1 hour
Attendees: Functional Lead, Technical Lead, all Scrum Masters, QA Leads
Purpose: Coordinate multi-team releases, integration testing sign-off
| Day | Morning | Afternoon |
|---|---|---|
| Day 1 (Mon) | Sprint Planning (2-4 hrs) | Development begins |
| Day 2-3 | Daily Standup (15 min) | Development |
| Day 4 (Thu) | Daily Standup | Scrum of Scrums (30 min) |
| Day 5 (Fri) | Daily Standup, Backlog Refinement | Development |
| Day 6-7 | Daily Standup | Development, QA testing |
| Day 8-9 | Daily Standup | Development wrap-up, QA testing |
| Day 10 (Fri) | Sprint Review (1-2 hrs) | Retrospective (1 hr), Release Coordination |